Steering Committee Project Update – Oct 2026
Project Update
On September 24, 2026 the Project Kick Off meeting was held at Tillamook 9-1-1. In attendance were the Steering Committee, the Motorola Project Manager / Motorola Project Engineer / Support personnel / Motorola Senior Account Managers / Tillamook Radio System Project Manager.
The following topics were covered:
- Motorola Implementation Team Introduction
- Review of Administrative Process for the Project
- Motorola Engineering review of the Contracted System and Deliverables
- Motorola Engineering review of critical path items and next steps
- Open Forum
There will be weekly team meetings to review progress and schedule and discuss open issues beginning in October.
The anticipated project schedule is as follows:
- October 2026: Begin engineering, system design, and site acquisition.
- 2027: Construct communications sites and install the radio system.
- By June 2028: Complete construction and installation, conduct system testing, and initiate system use.
A more detailed project schedule will be finalized and distributed by November 1, 2026.
User Agency Check-ins
Over the month of October, the Tillamook Communications System Administrator / Motorola Account Manager / Tillamook Radio System Project Manager personally visited each of the user agencies (listed below) to introduce the team, to review the system update, to review their projected radio needs, and answer questions.
Law Enforcement:
Tillamook Sheriff’s Dept Tillamook Police Dept Manzanita Police Dept
Fire Departments:
Garibaldi Fire Dept Nehalem Bay Fire Dept
Nestucca Rural Fire Dept Netarts/Oceanside Fire Dept
Rockaway Fire Dept Tillamook Bay Fire Dept
Ambulance: Adventist Health/Ambulance
Emergency Management: Tillamook County Emergency Management
Public Works: Tillamook County Public Works
PUD: Tillamook Public Utility District
Citizen Oversight Committee
County Administration and the Project Manager are working on developing a Citizen Advisory Committee for approval by the Tillamook County Board of Commissioners to provide project oversight
John Hartsock, Project Manager